Glass Production Scheduling: Station Load, Due Dates and Bottlenecks
"Can we get this order out by Thursday?" is a question asked every day in a glass factory. The answer depends on how much work is waiting right now at cutting, edging, tempering and IGU assembly, and how much each station can turn out per day. In this article we look at the data glass production scheduling depends on and how it is tracked in glass software.
Why schedules fall apart in glass factories
In many glass factories the schedule lives in the production manager's head or on a whiteboard. It falls apart because:
- Nobody knows how much work is waiting at each station; it is estimated,
- Rush orders jump the queue and the previous order is forgotten,
- Missing panes from partly finished orders get overlooked,
- Nobody measures which station is really the bottleneck.
The precondition for a good schedule: accurate data
No scheduling tool gives the right answer from the wrong data. To schedule, you need to know three things in real time: which station each pane is at, how much work is waiting at each station and each order's due date. In OGTOGLASS each product has a route (cutting → edging → tempering → assembly…) and this information builds up by itself as panes are marked on the station screens. See our glass production tracking article for details.
Seeing station load in m²
The OGTOGLASS home screen shows work waiting at each station in m² and daily output. If 180 m² is waiting in front of the tempering furnace and 40 m² at assembly, it is clear where the next job should go. On the station screen each operator sees only the panes waiting at their own station; "only those whose previous step is finished" prevents working out of sequence.
Prioritising by due date
The order list has date and status filters, and statuses are colour-coded: pending, in production, ready, completed, overdue, cancelled. The detail panel of the selected order shows its production status and which pane is stuck at which station. If a due date changes, that goes into the change history too: "Due date 07.10 → 09.10".
Try the OGTOGLASS glass software
Let's define your stations and routes and look at the load together.
Capacity and daily output
The detail panel of the selected order includes capacity information, and the home screen tracks daily output. Once you know a station's average daily output, you can roughly estimate how long the waiting work will take:
Estimated days = m² waiting at the station ÷ average daily output (m²)
For example, if 180 m² is waiting at tempering and the furnace averages 120 m² a day, an order entered today will leave tempering in about 1.5 days.
Finding the bottleneck with reports
The production report gives pieces and m² by station and day. Weeks of data show which station is always behind. In the advanced report you can build a station × day pivot yourself and export it to Excel. See our glass company reports article for more.
A weekly scheduling routine in 5 steps
- Start with overdue orders: deal with the ones flagged in the order list first.
- Read the station load: compare waiting m² on the home screen with daily output.
- Batch the cutting: nest orders waiting for cutting together in the cutting plan.
- Close partial orders: bring forward the few missing panes so the order can ship.
- Check the report: use the weekly production report to identify the bottleneck station.
OGTOGLASS does not impose an automatic schedule; it puts the data a planner needs on one screen. See production tracking or request a demo.
Frequently asked questions
How do you schedule production in a glass factory?
First you need to know the work waiting at each station (m²) and each station's daily output. Orders are sorted by due date, the load at each station is compared with its capacity, and the bottleneck station is found from daily production reports.
Does OGTOGLASS generate an automatic production schedule?
No. OGTOGLASS gives the planner the data needed to decide in one place: m² waiting at each station, daily output, overdue orders, capacity information on the order and a station × day production report. Panes reach the station screens along their routes.
How can I see which orders are late?
Overdue orders are shown in their own colour in the order list, and overdue orders are also marked in the ready-to-ship list.